Guaranteed High Marks with Updated & Real PMI-RMP Dumps pdf Free Updates [Q32-Q48]

Share

Guaranteed High Marks with Updated & Real PMI-RMP Dumps pdf Free Updates

PASS RATE Project Management Professional PMI-RMP Certified Exam DUMP


PMI-RMP certification is beneficial for professionals in various industries, including construction, IT, healthcare, finance, and engineering. It is especially valuable for project managers, risk managers, project coordinators, and team members involved in risk management. PMI Risk Management Professional certification provides a competitive edge in the job market and can lead to higher salaries and better job opportunities.


The Project Management Institute (PMI) is a globally recognized organization that offers various certifications to professionals in the project management domain. One of the most sought-after certifications from PMI is the PMI-RMP (PMI Risk Management Professional) certification. PMI Risk Management Professional certification is specifically designed for professionals who want to specialize in risk management practices and techniques.

 

NEW QUESTION # 32
Which input could be utilized to perform quantitative risk analysis to reduce uncertainty?

  • A. Expert judgment
  • B. Stakeholder register
  • C. Organizational process assets
  • D. Risk categorization

Answer: C


NEW QUESTION # 33
Examine the figure given below.

What will be the expected monetary value of Risk C?

  • A. $175,000 if the risk event actually happens
  • B. -$175,000
  • C. -$113,750
  • D. -$27,000

Answer: D


NEW QUESTION # 34
An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.
What should the risk manager do next?

  • A. Add only the threats to the risk register
  • B. Plan risk responses to the threats
  • C. Utilize different tools to identify the risks
  • D. Update the risk register with the identified risks

Answer: D

Explanation:
Explanation
The risk manager should update the risk register with both the opportunities and threats identified during the SWOT analysis. This will help in tracking and managing all potential risks throughout the project lifecycle.
Update the risk register with the identified risks Comprehensive and Detailed Explanation: According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain of Risk Identification is to update the risk register with identified risks, causes, categories, and potential responses1. A risk register is a document used to track and report on project risks and opportunities throughout the project's life cycle2. In this scenario, the risk manager should update the risk register with the identified risks, both opportunities and threats, that result from the SWOT analysis. The risk manager should also include the causes, categories, and potential responses for each risk, as well as other relevant information such as probability, impact, priority, owner, etc. The risk manager should not add only the threats to the risk register, because opportunities are also a type of risk that can have a positive effect on the project objectives and should be recorded and managed accordingly3. The risk manager should not utilize different tools to identify the risks, because the SWOT analysis is a valid and useful tool for risk identification and there is no indication that it was insufficient or inappropriate for the project context4. The risk manager should not plan risk responses to the threats, because that is a separate process that comes after risk identification and requires further analysis and evaluation of the risks5. References: 1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 82: Risk Register in Project Management - Project Management Academy63: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, page 3974: How to Perform a SWOT Analysis - Project Risk Coach25: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, page 440.


NEW QUESTION # 35
What are critical success factors for the Plan Risk Responses process?

  • A. Collect high-quality information about risks, address threats and opportunities, address interaction of risks and responses, and specify timing of responses
  • B. Define roles and responsibilities, address threats and opportunities, address interaction of risks and responses, and specify timing of responses
  • C. Identify appropriate project model, define roles and responsibilities, address threats and opportunities, and addresses interaction of risks and responses
  • D. Define roles and responsibilities, address threats and opportunities, categorize risk causes, and addresses interaction of risks and responses

Answer: B


NEW QUESTION # 36
You work as a project manager for BlueWell Inc. Your project is running late and you must respond to the risk.
Which risk response can you choose that will also cause you to update the human resource management plan?

  • A. Crashing the project
  • B. Fast tracking the project
  • C. Teaming agreements
  • D. Transference

Answer: A


NEW QUESTION # 37
Ben is the project manager of the CMH Project for his organization. He has identified a risk that has a low probability of happening, but the impact of the risk event could save the project and the organization with a significant amount of capital. Ben assigns Laura to the risk event and instructs her to research the time, cost, and method to improve the probability of the positive risk event. Ben then communicates the risk event and response to management. What risk response has been used here?

  • A. Sharing
  • B. Enhance
  • C. Transference
  • D. Exploit

Answer: B


NEW QUESTION # 38
A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)

  • A. Aligning to project constraints and priorities.
  • B. Obtaining stakeholder acceptance
  • C. Minimizing implementation costs.
  • D. Applying modern risk management techniques.
  • E. Ensuring risk response strategies mitigate all risks.

Answer: A,B

Explanation:
Explanation
To ensure an effective risk management plan, the risk manager needs to consider aligning the plan to project constraints and priorities and obtaining stakeholder acceptance, as these factors will help ensure that the plan is relevant and supported by the project team and stakeholders.
According to the PMI-RMP Handbook, the risk management plan is a document that describes how risk management activities will be structured and performed on the project. It is one of the main outputs of the Plan Risk Management process. The risk management plan should consider the following factors to ensure its effectiveness:
Aligning to project constraints and priorities: The risk management plan should be aligned with the project objectives, scope, schedule, cost, quality, resources, and stakeholder expectations. It should also reflect the project's risk appetite, tolerance, and threshold levels, which indicate the degree of uncertainty that the project can accept. The risk management plan should prioritize the risk management activities based on the project's critical success factors and key performance indicators.
Obtaining stakeholder acceptance: The risk management plan should be developed with the involvement and input of key stakeholders, such as the project sponsor, customer, team members, subject matter experts, and other relevant parties. The risk management plan should be communicated and approved by the stakeholders to ensure their commitment and support for the risk management process. The risk management plan should also define the roles and responsibilities of the stakeholders in risk management, as well as the reporting and escalation mechanisms.
The other options are not valid factors for ensuring an effective risk management plan:
Applying modern risk management techniques: The risk management plan should apply the appropriate risk management techniques that suit the project's context, complexity, and characteristics.
The techniques should be based on the best practices and standards of the profession, such as the PMBOK Guide and the Practice Standard for Project Risk Management. The techniques do not have to be modern or innovative, as long as they are effective and efficient.
Ensuring risk response strategies mitigate all risks: The risk management plan should define the risk response strategies that will be used to address the identified risks. However, the risk response strategies do not have to mitigate all risks, as some risks may be accepted, transferred, or avoided. The risk response strategies should be based on the risk analysis and evaluation, which consider the probability and impact of the risks, as well as the cost and benefits of the responses.
Minimizing implementation costs: The risk management plan should consider the budget and resources available for the risk management activities. However, the risk management plan should not aim to minimize the implementation costs at the expense of the quality and effectiveness of the risk management process. The risk management plan should balance the costs and benefits of the risk management activities, and ensure that they provide value to the project.
References: PMI-RMP Handbook1, PMBOK Guide2, Practice Standard for Project Risk Management2


NEW QUESTION # 39
After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

  • A. If the risk response is tied to an activity on the critical path
  • B. Verify due dates for the actions have been identified
  • C. How the response will affect the quality of the components
  • D. Probability of a response triggering a secondary risk

Answer: B

Explanation:
Explanation
The first element the risk owner should look for in the response plan is to verify that due dates for the actions have been identified. This ensures that risk mitigation actions are timely and can be effectively monitored.


NEW QUESTION # 40
You are the project manager of the GHY project for your company. This project has a budget of $543,000 and is expected to last 18 months. In this project, you have identified several risk events and created risk response plans. In what project management process group will you implement risk response plans?

  • A. Executing
  • B. Planning
  • C. In any process group where the risk event resides
  • D. Monitoring and Controlling

Answer: B


NEW QUESTION # 41
Wendy is the project manager of the FBL project for your company. She has identified several risks within her project and has created a risk contingency reserve of $45,000 total. Her project is nearly complete and many of the risks have not happened in the project. What should Wendy do with the funds in the contingency reserve?

  • A. The funds remain in the contingency reserve until all of the risks have passed.
  • B. The funds for the risks that have passed and have not happened are transferred to the project budget.
  • C. The funds remain in the contingency reserve until the project is closed.
  • D. The funds for the risks that have passed and have not happened are released.

Answer: D


NEW QUESTION # 42
You are the project manager for your organization. You have identified a risk event you're your organization could manage internally or externally. If you manage the event internally it will cost your project $578,000 and an additional $12,000 per month the solution is in use. A vendor can manage the risk event for you. The vendor will charge $550,000 and $14,500 per month that the solution is in use. How many months will you need to use the solution to pay for the internal solution in comparison to the vendor's solution?

  • A. Approximately 11 months
  • B. Approximately 13 months
  • C. Approximately 15 months
  • D. Approximately 8 months

Answer: A


NEW QUESTION # 43
A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.
Where should the project manager find this information?

  • A. Industrial studies
  • B. Enterprise environmental factors (EEFs)
  • C. Organizational process assets (OPAs)
  • D. Commercial risk databases

Answer: B

Explanation:
Explanation
Enterprise environmental factors (EEFs) include information from external sources, such as academic research, industry studies, and market conditions. this case, the project manager should refer to the research journal published by the local university as an EEF to gather information about the new material and its associated risks.


NEW QUESTION # 44
You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

  • A. Requested changes
  • B. Risk audits
  • C. Quantitative risk analysis
  • D. Qualitative risk analysis

Answer: A


NEW QUESTION # 45
You work as a project manager for BlueWell Inc. Your project is using a new material to construct a large warehouse in your city. This new material is cheaper than traditional building materials, but it takes some time to learn how to use the material properly. You have communicated to the project stakeholders that you will be able to save costs by using the new material, but you will need a few extra weeks to complete training to use the materials. This risk response of learning how to use the new materials can also be known as what term?

  • A. Benchmarking
  • B. Team development
  • C. Cost-benefits analysis
  • D. Cost of conformance to quality

Answer: D


NEW QUESTION # 46
You are project manager for ABD project. You, with your team, are working on the following activities:
Probabilistic analysis of a project.
Probability of achieving cost and time objectives.
Trends in Qualitative Risk Analysis results.
On which of the following processes are you working on?

  • A. Perform Qualitative Risk Analysis
  • B. Plan Risk Management
  • C. Perform Quantitative Risk Analysis
  • D. Identify Risks

Answer: C


NEW QUESTION # 47
You are the project manager of the GHY project. In your organization you must follow certain enterprise environmental factors that establish the rules for risk management . One of the policies your project must adhere to requires periodic rapid analysis of risks within the project. These rapid, cost-effective session must be documented and performed monthly. What type of analysis are you required to perform according to your enterprise environmental factors?

  • A. Quantitative analysis
  • B. Qualitative analysis
  • C. Delphi Technique
  • D. Brainstorming

Answer: B


NEW QUESTION # 48
......


The Project Management Institute (PMI) is a world-renowned organization that offers a wide range of certifications for professionals in the project management field. One such certification is the PMI-RMP (PMI Risk Management Professional) certification exam. PMI Risk Management Professional certification is designed for professionals who specialize in identifying and assessing project risks, and developing and implementing risk management strategies.

 

Best PMI-RMP Exam Preparation Material with New Dumps Questions: https://www.testkingfree.com/PMI/PMI-RMP-practice-exam-dumps.html

Updates For the Latest PMI-RMP Free Exam Study Guide!: https://drive.google.com/open?id=1iPqVP5zuxSgI5rRoNSVbxQnGnulTPVmc