NEW QUESTION 49
Which of the following items are recorded on an Inspection Lot? Note: There are 2 correct Answers to this question.

  • A. Inspection Results
  • B. Quality Task
  • C. Customer Complaint
  • D. Usage Decision

Answer: A,D

 

NEW QUESTION 50
When a supplier creates a ship notice on Ariba Network for a scheduling agreement release, which document is created in the buyer ERP?

  • A. Consignment movement
  • B. Confirmation for scheduling agreement
  • C. Inbound delivery
  • D. Scheduling agreement movement

Answer: C

 

NEW QUESTION 51
When can a supplier create an Advanced Ship Notice in the Supplier Managed Inventory process using planned shipment?

  • A. After the goods receipt has been generated or updated
  • B. After the order confirmation has been sent to Ariba Network
  • C. After manufacturing visibility has been sent to Ariba Network
  • D. After the schedule line has been sent to Ariba Network

Answer: D

 

NEW QUESTION 52
When will an invoice be generated in the Evaluated Receipt Settlement (ERS) process?

  • A. After goods receipt
  • B. After inbound delivery
  • C. After purchase order confirmation
  • D. After purchase order

Answer: A

 

NEW QUESTION 53
Which SAP ERP movement type is used for Returns Collaboration?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: C

 

NEW QUESTION 54
What is the correct transaction sequence for Forecast Collaboration?

  • A. Buyer Forecast Data Extraction & Transmission No Buyer Commit Review Supplier Review, Commit and Submit
  • B. No Buyer Commit Review Supplier Review, Commit and Submit Buyer Forecast Data Extraction & Transmission
  • C. Supplier Review, Commit and Submit No Buyer Commit Review Buyer Forecast Data Extraction & Transmission
  • D. Buyer Forecast Data Extraction & Transmission Supplier Review, Commit and Submit No Buyer Commit Review

Answer: D

 

NEW QUESTION 55
Which SAP modules have the ability to integrate with Ariba Forecast Collaboration? Note: There are 2 correct Answers to this question.

  • A. SAP Advanced Planner and Optimizer (APO)
  • B. SAP Integrated Business Planning (IBP)
  • C. SAP Enterprise Resource Planning (ERP)
  • D. SAP Intelligent Product Planning (IPP)

Answer: B,C

 

NEW QUESTION 56
Which of the following processes are included in Quality Collaboration? Note: There are 2 correct Answers to this question.

  • A. Quality of invoice
  • B. Quality notification
  • C. Quality review
  • D. Cost of quality

Answer: B,C

 

NEW QUESTION 57
Where in Ariba Network can a Supplier commit to a Forecast? Note: There are 2 correct Answers to this question.

  • A. Planning Collaboration Tab
  • B. Forecast Tab
  • C. Extended Collaboration Tab
  • D. Reports Tab

Answer: A,B

 

NEW QUESTION 58
Which document can be triggered by a copy supplier in the multi-tier process? Note: There are 3 correct Answers to this question.

  • A. Create Invoice for Subcontracting Services
  • B. Create Advance Ship Notice (ASN) for Finished Goods
  • C. Create Goods Receipt for Finished Goods
  • D. Create Component Receipt
  • E. Create Invoice for Component

Answer: B,C,D

 

NEW QUESTION 59
What are the statuses supported by Quality Review request?

  • A. New, Confirmed, Defect reported, Complete
  • B. New, In process, Complete, Close
  • C. In process, Defect reported, Complete, Close
  • D. New, Confirmed, In process, Complete

Answer: D

 

NEW QUESTION 60
What options does a supplier have in the supplier managed inventory process? Note: There are 2 correct Answers to this question.

  • A. Manufacturing Visibility
  • B. Replenishment Order
  • C. Planned Shipment
  • D. Forecast

Answer: B,C

 

NEW QUESTION 61
What ASN information is at the header level?

  • A. Production date
  • B. Batch number
  • C. Ship date
  • D. Ship quantity

Answer: C

 

NEW QUESTION 62
Which of the following are possible time bucket views in Ariba Network? Note: There are 2 correct Answers to this question.

  • A. Weekly
  • B. Daily
  • C. Biweekly
  • D. Hourly

Answer: A,B

 

NEW QUESTION 63
Which key figure gets updated on the Supplier Managed Inventory detail screen after the schedule line is released and sent to the supplier?

  • A. In-transit
  • B. Goods Received
  • C. Firmed Order
  • D. ASN Received

Answer: A

 

NEW QUESTION 64
What are the benefits of Supply Chain collaboration? Note: There are 3 correct Answers to this question.

  • A. Enhance end-to-end visibility
  • B. Increase lead time
  • C. Reduce cost
  • D. Increase control
  • E. Increase inventory levels

Answer: A,C,D

 

NEW QUESTION 65
Which of the following events change the ownership of goods for a consignment scenario? Note: There are 2 correct Answers to this question.

  • A. Consignment stock consumed by the customer
  • B. Supplier receives invoice from the customer
  • C. Post goods receipt for consignment stock
  • D. Transfer posting to own stock

Answer: A,D

 

NEW QUESTION 66
Which processes apply to component consumption in the subcontracting process? Note: There are 2 correct Answers to this question.

  • A. In real-time, the supplier needs to send a consumption report after the components have been used.
  • B. In backflush, the supplier needs to send a consumption report after the components have been used.
  • C. In backflush, the contract manufacturer does NOT need to report on the consumption of the components.
  • D. In real-time, the contract manufacturer does NOT need to report on the consumption of the components.

Answer: A,D

 

NEW QUESTION 67
What indicates that the purchase order line item is for returns in the buyer's SAP ERP system? Note:
There are 2 correct Answers to this question.

  • A. The Negative Net amount is shown at the line item detail level.
  • B. There is a negative quantity at the line item level.
  • C. The Confirmation Control is required at the line item detail level.
  • D. The Returns Items flag is checked at the line item level.

Answer: B,D

 

NEW QUESTION 68
......


C_ARSCC_2108 Exam Certification Details:

Level:Associate
Sub-solution:Ariba
Duration:180 mins
Sample Questions: SAP C_ARSCC_2108 Exam Sample Question

 

C_ARSCC_2108 Dumps 100 Pass Guarantee With Latest Demo: https://www.testkingfree.com/SAP/C_ARSCC_2108-practice-exam-dumps.html