[Aug-2022] PRINCE2Foundation Certification with Actual Questions from TestKingFree [Q62-Q85]

Share

[Aug-2022] PRINCE2Foundation Certification with Actual Questions from TestKingFree

Updated PRINCE2Foundation Dumps PDF - PRINCE2Foundation Real Valid Brain Dumps With 340 Questions!

NEW QUESTION 62
Which is a key decision made during the 'directing a project' process?

  • A. Approve the project manager role description
  • B. Approve the proposed project mandate
  • C. Confirm that the benefits management approach addresses all expected benefits
  • D. Select and appoint the project executive

Answer: A

Explanation:
Reference https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project-process-in-prince2

 

NEW QUESTION 63
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.

  • A. decides who is responsible
  • B. and the project board are responsible
  • C. has responsibility
  • D. and the team manager(s) are accountable

Answer: C

Explanation:
Reference http://prince2.wiki/Directing_a_Project

 

NEW QUESTION 64
Which is a purpose of a Project Brief?

  • A. Provide a solid basis for the initiation of the project
  • B. Describe the reporting requirements of the various layers of management involved with the project
  • C. Describe how changes to products will be controlled
  • D. Enable the assembly of the project mandate

Answer: A

 

NEW QUESTION 65
Why is it necessary to apply the 'defined roles and responsibilities' principle?

  • A. Because the project manager should represent all the stakeholders of the project
  • B. Because the project management team should be cross-functional
  • C. Because the people involved in a project should know what is expected of them
  • D. Because the user and supplier interests should be involved on a need-to-know basis

Answer: C

 

NEW QUESTION 66
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Controlling a Stage
  • B. Starting up a Project
  • C. Directing a Project
  • D. Managing a Stage Boundary

Answer: A

 

NEW QUESTION 67
Which is a purpose of the 'initiating a project' process?

  • A. To produce a stage plan for each stage of a multi-stage project
  • B. To provide a fixed point at which acceptance for the project product is confirmed
  • C. To enable the project board to decide whether it is worthwhile to initiate a project
  • D. To enable an organization to understand the work needed to deliver the project's products

Answer: C

Explanation:
Explanation
Reference
http://prince2.wiki/Initiating_a_Project#Objective

 

NEW QUESTION 68
Which is an objective of the Initiating a Project process?

  • A. Develop the corporate quality management system as part of the Project Initiation Documentation
  • B. Request authority from corporate management to deliver the project
  • C. Summarize how the organization's project management method will be tailored for the project
  • D. Prepare the plans for the subsequent stages

Answer: C

 

NEW QUESTION 69
Which is a factor when deciding the duration of a management stage?

  • A. The level of risk in the project
  • B. The number of products to be produced in the project
  • C. The cost of the stage
  • D. The work packages to be delivered

Answer: A

Explanation:
Explanation
Reference https://www.prince2primer.com/the-design-of-prince2-management-stages/

 

NEW QUESTION 70
Which risk response is applied on a pain/gain basis?

  • A. Share
  • B. Accept
  • C. Enhance
  • D. Exploit

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-2017-risk-responses-and-planning/

 

NEW QUESTION 71
Which theme estimates the cost of delivering the project?

  • A. Plans
  • B. Business case
  • C. Change
  • D. PROGEESS

Answer: B

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Business_Case

 

NEW QUESTION 72
Which describes a characteristic of a project?

  • A. It enables established and proven best practices
  • B. It maintains business as usual profitability
  • C. It provides a quality service to customers
  • D. It involves a team with different skills

Answer: A

Explanation:
Reference https://www.projectsmart.co.uk/what-is-prince2.php

 

NEW QUESTION 73
Which is created during the Starting up a Project process?

  • A. Communication Management Strategy
  • B. Project mandate
  • C. Quality Register
  • D. Project management team role descriptions

Answer: D

 

NEW QUESTION 74
Which process has the objective of confirming that acceptance criteria have been met?

  • A. Directing a project
  • B. Closing a project
  • C. Managing product delivery
  • D. Controlling a stage

Answer: B

 

NEW QUESTION 75
What product defines the reporting requirements between the Project Manager and Team Manager?

  • A. Project Brief
  • B. Product Description
  • C. Work Package
  • D. Team Plan

Answer: C

 

NEW QUESTION 76
What information should be recorded in the quality register?

  • A. Potential threats to the project's objectives and how they will be managed
  • B. Off-specifications that will occur during the project
  • C. Lessons that the project will capture and use during the project
  • D. Planned activities to determine whether the products are fit for purpose

Answer: C

Explanation:
Section: Volume B
Explanation/Reference: https://mplaza.pm/prince2-quality-register-template/

 

NEW QUESTION 77
Which is one of the six aspects of project performance to be managed?

  • A. Efficiency
  • B. Work
  • C. Timescales
  • D. Estimate

Answer: C

Explanation:
Reference http://prince2.wiki/Introduction:_The_PRINCE2_Foundation_Training_Manual#Six_variables_.2F_six_performance_targets

 

NEW QUESTION 78
Which of the following statements about the Closing a Project process are true?
1.The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2.The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

  • A. Only 2 is true
  • B. Only 1 is true
  • C. Both 1 and 2 are true
  • D. Neither 1 or 2 are true

Answer: A

 

NEW QUESTION 79
Which describes a risk effect?

  • A. The change in the status of a risk in response to actions taken to control it
  • B. The issue which is affecting the project and has resulted in a risk
  • C. The uncertainty expressed as a negative or favourable occurrence
  • D. The impact(s) on the project objectives should the threat or opportunity occur

Answer: D

 

NEW QUESTION 80
Which product records any project outcomes perceived as negative by stakeholders?

  • A. CommunicationManagement Strategy
  • B. Project Product Description
  • C. Business Case
  • D. Project Plan

Answer: C

 

NEW QUESTION 81
The application of which principle helps to define what should be included in a project?

  • A. Manage by stages
  • B. Defined roles and responsibilities
  • C. Focus on products
  • D. Continued business justification

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 82
Which risk response type is appropriate to respond to an opportunity?

  • A. Fallback
  • B. Accept
  • C. Exploit
  • D. Transfer

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 83
Why is the 'learn from experience' principle applied to a project?

  • A. To enable the project team to repeat successes from previous projects
  • B. To enable the project team to develop a business case for the project
  • C. To enable the project team to use tolerances to delegate authority
  • D. To allow the project to be divided into management stages

Answer: A

Explanation:
Explanation
Reference https://link.springer.com/chapter/10.1007/978-3-319-23000-9_4

 

NEW QUESTION 84
Which process is used by a Team Manager to coordinate work on one or more of the project's products?

  • A. Initiating a Project
  • B. Controlling a Stage
  • C. ManagingProduct Delivery
  • D. Managing a Stage Boundary

Answer: C

 

NEW QUESTION 85
......

Pass Your PRINCE2Foundation Exam Easily With 100% Exam Passing Guarantee: https://www.testkingfree.com/PRINCE2/PRINCE2Foundation-practice-exam-dumps.html

100% Free PRINCE2Foundation Exam Dumps Use Real PRINCE2 Certification Dumps: https://drive.google.com/open?id=1-3kYx5xncqu2KG-ox9437d-xSKpTpG8v