Get Ready to Boost your Prepare for your MSP-Foundation Exam with 121 Questions
Use Free MSP-Foundation Exam Questions that Stimulates Actual EXAM
The MSP Foundation Exam (5th Edition) is a globally recognized certification program that validates one's knowledge and understanding of the MSP framework. MSP stands for Managing Successful Programmes, and it is a proven approach to program management that helps organizations deliver successful programs. MSP-Foundation exam is designed to test your knowledge of the MSP framework and assess your ability to apply it to real-world scenarios.
The MSP Foundation Exam (5th Edition) consists of multiple choice questions that cover various aspects of program management, including the MSP framework, program governance, stakeholder management, benefits management, and risk management. MSP-Foundation exam is divided into two parts - the first part consists of 75 multiple-choice questions that must be completed in 1 hour, and the second part consists of 8 multiple-choice questions that must be completed in 2.5 hours.
The MSP Foundation Exam (5th Edition) is an important certification exam for individuals who are interested in advancing their careers in program management. It is recognized globally and is considered to be one of the most important certifications in the program management field. Individuals who pass the exam are recognized as experts in program management and are highly sought after by employers.
NEW QUESTION # 53
What is the result of the 'decisions' theme applying the 'collaborate across boundaries' principle?
- A. It will support prompt resolution from decision-makers across participating organizations
- B. It will stop the decision-makers from micro-managing the programme and its outcomes
- C. It will provide comprehensive data that decision-makers can use to justify actions
- D. It will enable the whole team to make decisions in a swift and empowered manner
Answer: A
NEW QUESTION # 54
Which activity BEST achieves the 'deploy diverse skills' principle?
- A. Allocating the right resources to assurance activities, balancing independence, knowledge and cost
- B. Planning delivery appropriately to achieve the future state and required outcomes of benefit
- C. Facilitating information sharing, enabling transparent, evidence-based decision-making
- D. Supporting stakeholders to have the information they need to understand priorities
Answer: A
NEW QUESTION # 55
Which is MOST likely to lead to the re-definition and re-scoping of a programme?
- A. Updated programme team experience
- B. Redefined programme management strategies
- C. Changed corporate strategies
- D. Reorganized Programme Office
Answer: D
NEW QUESTION # 56
What role is MOST likely to communicate with operational line managers to ensure that new benefits are identified?
- A. Business Change Manager
- B. Senior Responsible Owner
- C. Programme Manager
- D. Risk Manager
Answer: C
NEW QUESTION # 57
Which document identifies activities to give confidence to stakeholders about how programme risks are managed?
- A. Benefits realization plan
- B. Stakeholder engagement and communications plan
- C. Financial plan
- D. Assurance plan
Answer: D
NEW QUESTION # 58
Which document is updated throughout the programme when new information on benefits and risks becomes available?
- A. Information Management Plan
- B. Benefits Management Strategy
- C. Programme Brief
- D. Business Case
Answer: A
NEW QUESTION # 59
Which activity contributes MOST to achieving the 'deal with ambiguity' principle?
- A. Overseeing the development of the required organizational capabilities
- B. Articulating benefits and designing a clear target operating model
- C. Reflecting the uncertainty of estimates and specific risks in the business case
- D. Ensuring that stakeholders understand how benefits will be measured
Answer: C
NEW QUESTION # 60
Which risk response encourages collaboration on risk management activities?
- A. Avoid
- B. Reduce
- C. Prepare contingent plans
- D. Share
Answer: D
NEW QUESTION # 61
Which is a programme management principle?
- A. Identifying a programme
- B. Vision
- C. Adding value
- D. Corporate strategy
Answer: C
NEW QUESTION # 62
Which process ensures that all facts are available when they are required by the programme board?
- A. Evaluate new information
- B. Close the programme
- C. Design the outcomes
- D. Plan progressive delivery
Answer: A
NEW QUESTION # 63
Which TWO are objectives of the 'plan progressive delivery' process?
- A. To ensure that the approach to acquiring and managing the resources is defined.
- B. To ensure that the risks to the programme have been captured in a risk register and prioritized.
- C. To ensure that the pace of delivery can be supported by the operational areas.A. 1 and 2B. 2 and 3C. 3 and 4D. 1 and 4
- D. To ensure that the controls are put in place to ensure that benefits realization continues in BAU.
Answer: A
NEW QUESTION # 64
Which activity requires the programme office to be independent of the initiatives?
- A. Project guidance
- B. Project support
- C. Administrative duties
- D. Control of standards
Answer: A
NEW QUESTION # 65
Which is an assurance management technique?
- A. Quality management
- B. Issue management
- C. Gated reviews
- D. Change control
Answer: C
NEW QUESTION # 66
Which assurance success factor requires assurance activities to be tailored to the needs of the stakeholders?
- A. Independence
- B. Coordination
- C. Accountability
- D. Proportionality
Answer: D
NEW QUESTION # 67
Which describes an external factor that influences a programme?
- A. The lifecycle and delivery mode selected for each project
- B. The defined strategy for capturing and sharing knowledge
- C. Existing ways of working embedded in business as usual activities
- D. Changes in the behaviours of an organization's competitors
Answer: D
NEW QUESTION # 68
What provides a visual representation of risk aggregations and interdependencies?
- A. Summary risk profile
- B. Risk management framework
- C. Probability impact grid
- D. Risk register
Answer: C
NEW QUESTION # 69
Which contributes MOST to achieving the 'collaborate across boundaries' principle?
- A. Supporting stakeholders in accessing the knowledge and information they need to do their work
- B. Ensuring that decision-making approaches work effectively across multi-organizational governance
- C. Planning delivery of capabilities to deliver the outcomes of benefit at the pace required by the business case
- D. Adopting a risk-based approach to assurance that focuses resources to bring greater certainty
Answer: B
NEW QUESTION # 70
Which describes an impact of a risk?
- A. The amount of risk that will be tolerated
- B. An event that might increase a programme's outcome
- C. Possibility that something will go wrong
- D. Effect on the programme if something goes wrong
Answer: D
NEW QUESTION # 71
What is the BEST reason for using programme management?
- A. It enables stakeholder engagement
- B. It concentrates on delivering outputs
- C. It removes the need for strong leadership
- D. It provides a vision for the entire organization
Answer: B
NEW QUESTION # 72
Which statement BEST describes the 'check' phase of the Plan Do Check Act cycle when used to manage a risk?
- A. It involves validating whether a risk has been managed effectively or whether further action is needed
- B. It is where risk responses are implemented to manage the identified and prioritized risks
- C. It is where initial risk responses that have been implemented are revised to reflect current priorities
- D. It involves understanding the risk tolerances and how it will affect the programme's risk appetite
Answer: A
NEW QUESTION # 73
Which transformational flow process provides the basis for deciding whether the programme can proceed?
- A. Identifying a Programme
- B. Defining a Programme
- C. Managing the Tranches
- D. Delivering the Capability
Answer: A
NEW QUESTION # 74
Under which heading in the POTI model should the current performance level of an operational area be recorded?
- A. Technology
- B. Process
- C. Information
- D. Organization
Answer: B
NEW QUESTION # 75
Which is a purpose of the 'close the programme' process?
- A. To ensure the programme is justified before deciding whether or not to proceed
- B. To ensure the organization(s) involved understand the programme vision, benefits, risks and the target operating model
- C. To ensure that the investing organization(s) are ready to maximize the benefits to be realized from the programme work
- D. To ensure that the investing organization(s) make the required changes to adopt new ways of working and realize benefits
Answer: D
NEW QUESTION # 76
Which is a structured set of programme activities that define the sequence of actions, and their inputs and outputs, to achieve a specific objective?
- A. Themes
- B. Principles
- C. Outcomes
- D. Processes
Answer: D